TITLE: 01/29 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: CALM
Wind: 0mph Gusts, 0mph 5min avg
Primary useism: 0.03 μm/s
Secondary useism: 0.40 μm/s
QUICK SUMMARY:
No locking will be done today do to engineering run work.
Expected Engineering work today:
LVEA is still laser Hazard.
EX Pump Down will be started today.
ham 6 Work will continue.
Please be careful working at height due to local LASER HAZARD work near the SQZ tables.
Wind Fence work will continue.