Reports until 19:15, Tuesday 30 January 2024
LHO VE
janos.csizmazia@LIGO.ORG - posted 19:15, Tuesday 30 January 2024 - last comment - 21:04, Tuesday 30 January 2024(75638)
1-30 vent vacuum diary
Today's activities:
- HAM3 Y+ door has been removed
- The pumpdown at EX has been started, with the Hepta. In the end of the day, the pressure is in the low E+0s - a.k.a. a few Torrs; so transitioning to Turbo tomorrow. The purge air won't be switched off until the leak tests
- In parallel with the HAM3 door removal, the purge air was hooked up to the X-manifold as well (now it is purging at the input beam; at the x-manifold; and at HAM7)
- BSC8 AIP railed - possibly there is a leak between the main volume and the annulus volume, will be further investigated. Will be taken care of tomorrow
Comments related to this report
jordan.vanosky@LIGO.ORG - 21:04, Tuesday 30 January 2024 (75639)

Today's dew point measurement at the OMC tube, prior to in-chamber activites, -45.8degC

Images attached to this comment