Reports until 17:23, Wednesday 31 January 2024
LHO VE (VE)
travis.sadecki@LIGO.ORG - posted 17:23, Wednesday 31 January 2024 - last comment - 19:04, Wednesday 31 January 2024(75655)
1-31 vent vacuum diary

Today activities:

-EX pumpdown continues.  Roughing via Hepta pump was restarted this morning, and by ~14:30 PT pumping was transitioned to the turbo station (initially backed by the Hepta then swapped to scroll pump backing once the inlet pressure was in the e^-2 Torr range).

-Quantity 2 of the 3IFO 12" CF-to-triple-4.5" CF reducer/feedthrough assemblies were removed from the north side of BSC8. These were replaced with 12" CF blanks.  

Comments related to this report
jordan.vanosky@LIGO.ORG - 17:40, Wednesday 31 January 2024 (75656)

Todays purge air dew point measurement, -43.9degC

Images attached to this comment
travis.sadecki@LIGO.ORG - 19:04, Wednesday 31 January 2024 (75658)

CF assemblies removed from BSC8 north side.  

Images attached to this comment