Today we completed assembly of the work platform around BSC 3 with the exception of 1 section of handrail that interferes with some annulus piping on GV2. I have talked with Kyle and we should be able to remedy this quite easily. Transported a 3 step platform to end x for Cheryl to use in the clean room. Tyler worked in the machine shop, still working on parts for SUS (Betsy) and a small job for Filiberto. The flooring guys are approximately 85% complete with vinyl, they will come back tomorrow to weld joints and trim out.