Displaying report 1-1 of 1.
Reports until 16:40, Thursday 01 February 2024
H1 General
anthony.sanchez@LIGO.ORG - posted 16:40, Thursday 01 February 2024 (75681)
Thursday Ops Day Shift End

TITLE: 02/02 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:

Engineering Run Work Update:
HAM3 is Almost complete, Waiting on Jims TF. before the HAM3 Doors go back on.

HAM6 & 7 teams are still in the LVEA and just transitioned the LVEA to LASER HAZARD (work permit 11666) and Camilla is expected to transition the LVEA Back to LASER SAFE before she leaves.

VAC team did some leak down tests on EndX.
 


Alarms:
16:43 UTC Restart of Dust monitors.
Dust Mon in PSL alarm went off at 17:41 UTC

18:06 : UTC Dust mon alert again

HAM7 Watch dog tripped 18:08 UTC
Dust Mon 10 Alarm are at 140 for 300nm & 89 for 500nm

19:31 UTC Dust mon 102 in Anteroom  Vacuum  H0:VAC-EX_X4_PT525_MOD1_PRESS_TRR Alarm went off twice while Jordan and Gerardo were down at EX.

LOG:                                                                                                                                                                                                                                                                                                                                                                                                                                                                       

Start Time System Name Location Lazer_Haz Task Time End
15:54 FAC Kim & Karen LVEA No Technical Cleaning 17:01
16:35 VAC Jordan LVEA No Vaccum work 17:07
16:37 TCS TJ LVEA No Chasing TCS leaks 18:31
16:47 PEM Robert & Mitchel LVEA HAM3 No HAM3 Baffle Work 19:19
17:01 FAC Kim, Karen, Emma HAM SHAQ No Technical Cleaning. 19:02
17:07 VAC Jordan END X N Checking End X Pump Down 17:44
17:38 VAC Travis LVEA +Y N Removing Feedthrough on BSC8 20:02
17:44 SUS Rahul , Austin, Camille HAM7 No ZM4 in HAM7 work + HAM6 OMC Recentering 20:15
17:45 VAC Jordan LVEA +Y N BSC8 feedthrough work 20:02
17:58 FAC Eric MidX No checking Air Handler 18:30
18:28 VAC Betsy Mech Rm No Checking Equipment & looking for parts 18:55
18:56 EE Mark PEM Rack CER N workin on PEM Accelerometers 19:08
19:10 OMC Keita LVEA HAM6 No Electronics check 00:37
19:18 VAC Gerardo LVEA BSC8 No Feed through removal 20:02
20:18 PEM Robert & Mitchel LVEA HAM3 No HAM3 Baffle work 00:17
21:13 IAS Jason & RyanC LVEA West No Surveying the LVEA 22:47
21:23 FAC Tyler LVEA N Crane inspection 23:21
21:27 VAC Jordan & Gerardo LVEA BSC8 N Working on  removing feedthroughs 21:59
21:30 SUS Corey LVEA HAM3 N Taking in chamber pictures 23:10
21:59 VAC Gerardo & Jordan EndX N Leek Checking 00:18
22:00 VAC Betsy LVEA HAM3 N Pestering HAM3 Workers. 00:13
22:36 SQZ Sheila Julian OPTIC Lab N Gathering equipment 23:48
22:52 SQZ Camilla LVEA N Talking to Betsy, and helping Camille. 23:21
23:15 FAC Richard LVEA HAM3 N Pestering Betsy & HAM3 crew. 23:55
23:38 VAC Travis HAM SHAQ N Dropping off equipment 23:58
00:01 SEI Jim LVEA N Tripping Watchdogs in HAM3 00:18
00:12 SAFE Camilla LVEA yes LASER SAFE TRANSITION 00:18
00:20 SQZ Camilla, Sheila, Julian, Vicki HAM6 yes HAM7 & SQZ work 02:20
00:21 LASER SITE LVEA YES LVEA IS LASER HAZARD 00:21
00:31 VAC Gerardo LVEA YES Twittling Some Valves 01:31
Displaying report 1-1 of 1.