Reports until 19:36, Friday 02 February 2024
LHO VE
janos.csizmazia@LIGO.ORG - posted 19:36, Friday 02 February 2024 - last comment - 04:33, Saturday 03 February 2024(75717)
2-2 vent vacuum diary
Today's activities:
- HAM3 Y+ door was reinstalled. No issues during the process, however, some scratches have been found - see pics.
- After the door was reinstalled, the Annulus volume is being pumped
- The Gate Valve for the 1000 amu RGA was installed on the Y-mainfold, with an additional angle valve
- 2 out of 3 16.5" 3IFO feedthrus were removed from BSC8 - at the north side. A very scratchy conflat was found, see pic. To mitigate the risk, Technetics-Helicoflex-type CF seal repair gaskets will be ordered. At the south-side of the chamber, the unnecessary cable trays were removed, in preparation for the 3rd feedthru removal
- EX pumpdown status: it is already at ~2E-7
Images attached to this report
Comments related to this report
gerardo.moreno@LIGO.ORG - 04:15, Saturday 03 February 2024 (75719)VE

(Jordan V., Gerardo M.)

Installed a gate valve at the YBM (Y beam manifold) to be used for the new 1000 amu RGA.  A zero length reducer with a metal seal right angle valve were added to facilitate the addition of parts in a near future.  No issues were encountered during the installation.

Images attached to this comment
gerardo.moreno@LIGO.ORG - 04:33, Saturday 03 February 2024 (75720)VE

EX pumpdown curve.  The two spikes noted on 2/1/2024 were turbo pump isolation valve cycles, the gate valve was opened and closed to perform leak tests of the conflats/ports disturbed on this vacuum envelope, more on this aLOG.

Images attached to this comment