Displaying report 1-1 of 1.
Reports until 16:00, Monday 05 February 2024
LHO General
ryan.short@LIGO.ORG - posted 16:00, Monday 05 February 2024 (75735)
Ops Day Shift Summary

TITLE: 02/05 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: Main activities today were HAM7 beam alignment work with more to come tomorrow, the TCS water lines were filled and chillers are running again; LVEA is still laser hazard.
LOG:

Start Time System Name Location Lazer_Haz Task Time End
16:20 FAC Kim, Karen LVEA - Technical cleaning 17:48
16:32 TCS TJ, RyanC, Jason LVEA/MER - Start checks on TCS water lines 17:29
16:33 SQZ Sheila LVEA - Looking for equipment on ISCT1 17:17
16:33 FAC Eric EX - Checking roll-up door 17:01
16:43 VAC Jordan LVEA - Purge air measurement at output arm 16:51
17:02 VAC Janos LVEA - Checking pumps 17:09
17:12 SEI Jim, Tony, Neil, Michael, Shoshana EX - Checking BRS 19:38
17:13 FAC Randy, Ibrahim LVEA - Craning in W-bay 18:19
17:13 CDS Fil LVEA - HAM6 ground loop checks (OMs to SAFE) 18:03
17:26 CDS Erik EY - Check on HWS computer 17:50
17:28 SAF Sheila, Camille, Julian, Rahul LVEA YES Transitioning to HAZARD 17:44
17:43 IAS Jason, RyanC LVEA YES FARO surveying in W-bay 20:02
17:44 SAF LVEA is Laser HAZARD LVEA YES LVEA is Laser HAZARD 17:44
17:45 SQZ Sheila, Rahul, Camille, Julian, Naoki LVEA YES Beam alignment in HAM7 20:38
18:06 AOS Betsy LVEA YES Helping HAM7 team 18:36
18:23 FAC Karen EY - Technical cleaning 19:40
18:41 FAC Randy, Ibrahim LVEA YES Craning in W-bay 19:53
18:48 FAC Tyler FCES - Inventory 19:02
18:51 FAC Chris LVEA YES FAMIS checks 19:13
19:31 VAC Travis, Jordan FCES - Check RGA equipment 19:52
20:31 CDS Fil EX - Cabling for BRS and OpLev 00:30
21:08 TCS TJ, Jason LVEA YES Plugging in chiller lines 22:48
21:17 VAC Gerardo LVEA YES Leak detector on Y manifold 22:19
21:21 VAC Jordan EX - Leak checks 00:20
21:31 VAC Travis LVEA YES BSC8 flanges 22:35
21:41 SQZ Sheila, Rahul, Naoki, Julian, Camille LVEA YES HAM7 beam alignment work 23:44
22:19 VAC Gerardo EX - Retreiving equipment 23:03
22:23 SEI Jim, Tony, Michael Overpass - Tour and vault searching 23:22
22:51 AOS Jenne, Neil, Shoshana, Wasim LVEA YES Tour for visitors 23:51
23:29 VAC Janos LVEA YES Checking on a pump 00:29
23:58 VAC Gerardo LVEA YES Leak checking near +Y manifold 00:58
Displaying report 1-1 of 1.