H1 General
betsy.weaver@LIGO.ORG - posted 17:05, Thursday 08 February 2024 - last comment - 11:52, Friday 09 February 2024(75791)
HAM6 closeout

(Betsy, Keita, Rahul, Sheila

We finished installing the new square-hole OMC glass shround end panels this morning after a good round of cleaning.

Then we spent most of the day hunting for the OMC Trans Cam beam - we finally found it, aligned it to the viewport door simultor, and were able to launch Jim and Rahul for final SUS/SEI closeout.

We transitioned to Laser Safe (thanks TJ), Closed HAM6, 7 and the HAM5 mini port gatevalve.

A new contam control wafer was laid near the center of the table and cables, tools, interferences, were all checked.  Most signoffs have been complete - Jim and SUS crew checking TFs now and expect to be cleared this eve.  Jim has signed off, Rahul on now.  He'll txt me any issues, so otherwise all good, doors to proceed.

Doors on HAM6 tomorrow morning followed by corner pump down ~Monday hopefully.

Images attached to this report
Comments related to this report
corey.gray@LIGO.ORG - 11:52, Friday 09 February 2024 (75803)EPO

Tagging EPO for HAM6/OMC photos