TITLE: 02/09 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
Big activity today was getting HAM6 closed up & preparing to pump the Corner Station (HAM7 still has doors off & additionally, the Relay Tube is also not installed.)
LOG:
- 1530-2011 Preparing/Installing HAM6 doors (randy)
- 1627 Jordan joining, 1726 Gerardo joining
- 1545 LVEA technical cleaning (kim.karen)
- 1631-1635 Grabbing Genie lift at FCES (tyler)
- 1645-1937 Balancing EX BRS (jim, michael, shoshana, neil)
- 1737 Climbing around and running fibers at EX for upcoming cds upgrade job (fil)
- 1827 Dropping off genie lift at EY (tyler)
- 1906-2000 Checking scribe marks on BSC2 (jason)
- 2052-2147 EX fiber pulling clean-up + turning off a cleanroom in the EX VEA (fil)
- 2056-2133 Drilling holes at FCES for purge (randy)
- 2058-2155 Finish balancing BRS (jim, michael, shoshana)
- 2110-2151 VAC set-up around HAM6 (jordan, janos)
- 2135-2310 Pump down prep (gerardo, richard, randy)
- 2150 pulling oplev cables (fil)
- 2155-2224 Remove bypasses for High voltage in CER+MechRoom (fil)
- 2224 Pulling oplev cable along Y-Beam manifold (fil)
- 2225-2318 MX accelerometer install (marc)
- This required dave to power down/up the chassis
- 2237-2315 RGA work at EX (jordan.janos)
- 2314-2322 Checking FARO & powering down for the weekend (jason)
- 2345 Tour in Control Room by Jonathan & Mike for a visitor