Ham 6 doors are on with 4 bolts each. Flange joints on hams 4,5,&6 are taped all around, started sealing vacant bolt holes on same flanges. Relocated clean room that was over ham 4 to area in front of hi bay. Tyler in machine shop, talked with Betsy regarding a longer tap, still working on SUS parts. Flooring guys at end y will finish this afternoon, with the exception of approximately 14' of trim. This trim had to be oredered and is 2 weeks out. This trim is where the seams come together and does not pose any contamination isssue.