TITLE: 02/12 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: The HAM7 doors are ready to be put back on, the CS pumpdown has begun, and EndX & HAM8 are being prepped to be vented.
17:59UTC SUS ZM5 WD trip, LVEA RED pressure alarm 18:30UTC, a few PSL anteroom yellow dust alarms throughout the morning/early afternoon then several red alarms around 22-23UTC.
21:12UTC ISI HAM7 WD trip, maybe from Gerardo turning down the purge air? ISI HAM5 & 7 tripped a few minutes later 21:18UTC and the motion was too high to untrip for a bit (~ 4 minutes), probably from the VAC teams work, sudden changes in pressure? Tagging VE, SEI. They retripped 2 minutes after I reset them after the motion look like it had calmed down. I'm going to leave them tripped for now.
21:51UTC the CS pumpdown started!
LOG:
Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
---|---|---|---|---|---|---|
15:30 | FAC | Kim & Karen | LVEA | N | Tech clean | 16:16 |
16:04 | FAC | Contractors | EndY then X | N | Crane inspection | 19:07 |
16:16 | FAC | Ken | LVEA | N | Check pump | 17:41 |
16:58 | VAC | Travis | LVEA | N | Vac checks | 17:17 |
17:15 | SUS | Rahul | LVEA, HAM7 | N | HAM7 checks | 18:35 |
17:17 | VAC | Travis | EndX | N | Check on RGA | 17:50 |
17:28 | EE | Fil | LVEA, mech rm | N | HAM7 grounding checks, SUS to SAFE HAM7 | 19:40 |
17:40 | Camilla, Betsy | HAM7 | N | Closeout work, Betsy out @ 17:51UTC | 17:54 | |
17:50 | VAC | Gerardo | LVEA | N | Check viewports are covered, pumpdown prep | 19:09 |
17:50 | EE | Ken | EndX then LSB | N | Lights | 23:23 |
17:53 | FAC | Karen | LVEA | n | Tech clean | 18:12 |
18:00 | VAC | Jordan | LVEA | N | Join Gerardo | 19:09 |
18:31 | VAC | Travis | EndX | N | RGA | 23:11 |
18:34 | FAC | Karen | EndY | N | Tech clean | 19:41 |
18:38 | FAC | Richard | LVEA | N | Talk with Vac & Fil | 19:38 |
18:43 | SUS | Rahul | LVEA | N | Check with Fil | 18:48 |
19:01 | SUS | Rahul | LVEA, HAM7 | N | Adjust BOSEM flag | 19:15 |
19:17 | SEI | Jim | LVEA, HAM7 | N | unlock ISI | 19:47 |
19:17 | SQZ | Camilla | LVEA | N | Check beam diverter | 19:49 |
19:47 | FAC | Chris + contractors | LVEA | N | Crane inspection | 19:57 |
19:48 | FAC | Tyler | FCES | N | Check equipment | 19:50 |
19:48 | SEI | Jim | CR | N | HAM7 transfer functions | 20:32 |
19:49 | SQZ | Camilla & Julien | FCES | N | Check SQZT8 | 20:43 |
20:36 | SUS | Rahul | CR | N | SUS H7 transfer functions | 22:36 |
20:53 | SEI | Jim | EX, EY | N | EX - check BRS, EY - wind fence | 23:13 |
21:07 | VAC | Jordan | LVEA | N | Prep for pumpdown | 21:51 |
21:11 | VAC | Gerardo | LVEA | N | Join Jordan | 21:51 |
21:51 | VAC | Garardo, Janos, Jordan | LVEA | N | Start CS pumpdown (excluding HAM7), Gerardo out 23:10UTC | Ongoing |
23:23 | EE | Ken | EndX | N | Move lift from EndX to EndY | Ongoing |
23:26 | EE | Fil | FCES | N | Disconnect SQZT8 | Ongoing |