Reports until 16:02, Thursday 29 August 2013
LHO General
hernan.daveloza@LIGO.ORG - posted 16:02, Thursday 29 August 2013 (7584)
Ops Summary

- Apollo crew working on the floor of End-Y.
- Apollo installed HAM door in LVEA.
- Arnaud was taking TF of the BS.
- Dust monitors location updated (I guess Patrick did it).
- Richard went to mid-X to check equipment.
- Dave installed firefox on left operator's computer for camera views.
- Dave copy firefox's folder after crash (lost bookmarks) on main operator computer.
- Rick and Christina (her last day) working on PSL.

 

pablo