ryan.short@LIGO.ORG - posted 16:01, Friday 16 February 2024 (75877)
Ops Day Shift Summary

TITLE: 02/16 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: Another busy day; CS volumes still pumping down.

LOG:

Start Time System Name Location Lazer_Haz Task Time End
16:25 FAC Randy LVEA/FCES - Moving scissor lifts in/out of VEAs 19:21
17:23 IAS Jason, RyanC LVEA - Surveying in BG 19:13
17:29 VAC Jordan, Gerardo EX - RGA scans 19:21
17:42 FAC Karen, Kim FCES - Technical cleaning 18:05
17:47 SQZ Nutsinee Optics Lab - Gathering equipment 18:10
18:01 CDS Fil LVEA - Cabling cleanup 19:19
18:04 VAC Janos LVEA - Check on vacuum pump 18:45
18:10 SQZ Nutsinee, Daniel, Naoki LVEA Yes Local hazard work on SQZT0 21:24
18:21 FAC Karen, Kim LVEA - Technical cleaning 18:44
19:04   Ryan S LVEA soon Transitioning to Laser Hazard 19:19
19:20 CDS Fil, Camilla LVEA Yes Check power on HWS tables 19:51
19:22 SAF LVEA is Laser HAZARD LVEA Yes LVEA is Laser HAZARD Ongoing
20:05 VAC Janos LVEA Yes Checking on vacuum pump 21:05
20:14 TCS Camilla LVEA Yes Power on HWS tables 20:21
21:05 VIS Tony, Julian, Ibrahim, Dana, Dripta, Oli Roof - Showing visitors the view 21:13
21:06 VAC Jordan, Gerardo EX - RGA scans 22:31
21:41 IAS Jason, RyanC LVEA Yes FARO surveying in W-bay 22:28
21:50 SQZ Naoki, Daniel, Nutsinee LVEA Yes SQZ PMC work Ongoing
22:39 VAC Jordan, Gerardo FCES - RGA scans 23:36
22:40 VAC Gerardo LVEA Yes Looking for Janos 22:50
23:01 SQZ Camilla, Julian Optics Lab - Building spare SHG Ongoing