Today's activities: - HAM7 pumpdown status: ~3.3E-6 Torr - Corner pumpdown status: ~3.9E-1 Torr. On Tuesday, transitioning to Turbo (Y-manifold; OMC; HAM6) - EX pumpdown status: 3.75E-8 Torr: the post-vent RGA scan is ready, the results will be in the comment comment section, once they are published. The comparison with past RGAs is also coming next week. If the results will be considered satisfactory, the Ion-pump will be valved in. The GV will remain closed during FAC works - The purge air supply at FCES is switched on, in order to start HAM8 vent first thing next week