H1 SQZ
camilla.compton@LIGO.ORG - posted 11:52, Tuesday 20 February 2024 (75894)
SQZT8 Moved away from HAM8 for door removal

WP11693 Vicky, Camilla, Chris. 

In preparation for the for HAM8 +Y door removal, after HAM8 was been vented, we put guillotine in the viewport and removed the bellows between HAM8 and SQZT8. Bellows is wrapped in foil on top of SQZT8. We rolled SQZT8 enclosure out of the way of the door crew (it's position was already marked and parts on table secured 75831, 75829).