Displaying report 1-1 of 1.
Reports until 16:00, Wednesday 21 February 2024
H1 General
ibrahim.abouelfettouh@LIGO.ORG - posted 16:00, Wednesday 21 February 2024 (75917)
OPS Day Shift Summary

TITLE: 02/21 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:

CDS work has largely concluded and suspensions/seismic have been put back into their normal GRD settings.

With some exceptions:

Additionally, the LVEA is now LASER SAFE

LOG:

Time In (PT) Time Out (PT) System Name Location Lazer Hazard Task
7:50 8:30 FAC Kim, Karen FCES N Technical Cleaning
ONGOING ONGOING SAF LVEA is Laser Hazard LVEA Yes LVEA is Laser HAZARD
8:30 8:50 CDS Jonathan Mechanical Rm N CDS Work
8:30 10:00 FAC Karen EY N Technical Cleaning
8:30 8:56 VAC Jordan LVEA Yes Pump check
9:00 9:15 SUS Randy LVEA Yes Inventory Round
9:02 10:41 SUS Jason LVEA Yes West Bay FARO Work
9:06 9:24 SQZ Preet, Camilla LVEA Yes Change Hartmann Power Supply
9:09 10:41 SUS Ryan C LVEA Yes West Bay FARO Work
9:12 11:12 VAC Janos LVEA Yes Pump check
9:15 11:03 SUS Randy MX, MY N Inventory Round
9:49 10:50 SQZ Julian, Camilla Optics Lab N Spare SHG Build
9:55 10:20   Nutsinee LVEA Yes Table Work
9:55 10:22 FAC Richard LVEA Yes Walkabout
10:13 11:34 FAC Kim EX No Technical Cleaning
10:15 11:10 VAC Jordan, Gerardo LVEA Yes Climbing on HAM6
10:00 11:03 FAC Karen LVEA Yes Technical Cleaning
10:30 11:10 SUS Mitchell EY, EX N Dust Monitor FAMIS Task
10:54 ... SEI Fil FCES N Seismic Chassis Work
11:03 11:30 FAC Karen Wood Shop N Technical Cleaning
11:30 11:42 FAC Karen MY N Technical Cleaning
11:38 15:41 CDS CDS OUTAGE CTRL RM N CDS OUTAGE
12:02 12:26 VAC Janos LVEA Yes Pump check
12:47 13:10 VAC Travis LVEA Yes LVEA Laser Safe Transiiton
13:16 14:16 SQZ Julian, Camilla Optics Lab N SHG Work
13:17 ... SUS Randy LVEA N Septum into High-Bay
13:21 13:50 VAC Jordan LVEA N HAM6 Gate Valve
13:21 14:26 VAC Gerardo LVEA N HAM6 Gate Valve
13:27 ... VAC Travis LVEA N Relay Tube Assembly
14:14 15:00 CDS Jonathan Mechanical Rm N Switching Switches
14:26 15:01 VAC Janos LVEA N Pump Check
14:30 14:34 SUS Austin LVEA N Parts