Today's activities: - HAM7 pumpdown status: ~8.5E-7 Torr - Corner pumpdown: ~7.4E-7 Torr, ~51 hours after the HV pumping started - EX pumpdown status: 3E-8 Torr. The GV will remain closed during FAC works (1-2 weeks) - At the EX RGA the bakeout temperature is ramping up; in the upcoming days the HAM7 and HAM8 RGAs will also be baked, as per WP #11713 - The inner annulus system of GV5 was valved in to the main annulus system - The hardware was prepared for the newest version Relay Tube's installation, which will be done tomorrow