Today's activities: - HAM7 pumpdown status: ~7.7E-7 Torr - Corner pumpdown: ~6E-7 Torr, ~73 hours after the HV pumping started - EX pumpdown status: 2.9E-8 Torr. The GV will remain closed during FAC works (1-2 weeks) - At the EX RGA the bakeout temperature has been ramped up to 150 deg C; in the upcoming days the HAM7 and HAM8 RGAs will also be baked, as per WP #11713 - The pumping cart was disconnected from the GV5 annulus system - The relay tube has been installed, see attached photo - The relay tube is being pumped, at the moment is already at 2.4E-6 - The relay tube was leak checked, and everything is OK