TITLE: 02/26 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
CURRENT ENVIRONMENT:
SEI_ENV state: CALM
Wind: 30mph Gusts, 24mph 5min avg
Primary useism: 0.05 μm/s
Secondary useism: 0.37 μm/s
QUICK SUMMARY:
17:27 4.9 Mag Earthquake from Idaho, trips ISI's but no suspensions.
18:00 UTC PSL gets green light from CDS but the PSL folks say things are still not right.
18:30 UTC the PMC started to work correctly again.
Seismic to calm 19:50 UTC
Monthly test of Hanford system 12:30 - 1 pm
Transition to hazard 12:30 Local time
Out of medium garb
The Combiner was ran down X arm.
Oplev work is still in progress.
HAM6 Camera work is still in progress.
Vacuum System has passed some leak tests and is still pumping down.