TITLE: 03/07 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
Today commissioning team mainly worked on ASC (in the afternoon mainly at the PREP ASC FOR FULL IFO state). Other notables: X-Arm controlled burns continued and HAM7 annulus ion pump leak work,
Nuc30's DARM dtt session had to be closed/restarted, and it also timed out as well---so you have to keep an eye on it.
LOG:
- 1520-1720 Equipment moving around site (randy, eric)
- 1525 Alignment (Sheila, Gabriele)
- 1631-1641 EY camera reboot (dave)
- 1657-1728 cleaning optics lab/vacuum prep (karen)
- 1709-2247 Prescribed Burning on X-arm with (2) large fire trucks and (2) pick-ups.
- 2234 2nd (of2) large fire trucks left for day
- 1713-1723 Opening Receiving roll-up for cardboard (kim)
- 1740-1750 H2 Elec Room cleaning (kim)
- 1747-1808 Hardware storage checks in LVEA (randy, mitch)
- 1808 Similar check peaking in to EY VEA (not stepping on slab!)
- 1815-1917 MY & EY turbo pump maintenance (janos, jordan)
- 1947-2010 Start spinning turbos down at MY/EY (jordan)
- 2117-2137 Finally turning OFF turbos (jordan)
- 1818-1829 Field trip in Control Room (cassidy)
- 1839-1918 HAM7 Annulus Ion Pump leak work (gerardo, travis)
- 1908 HAM7 WatchDog trip
- 1918 Pumping and will check on status in ~1hr
- 1917-1940 Moving BSC Cartridge tooling from outside and into the Staging Building via forklift (randy)
- 1956-2012 Fire Pump #1 Verbal---this was because Hanford Fire Dept is filling their trucks with water; this took about 15-20min.
- 2019-2119 SQZT7 Local Laser Hazard work---no work at Height!! (nutsinee, trent, vicky, daniel)
- 2108-2134 Installing new HAM7 annulus ion pump controller (travis)
- 2143 Walking over to FCES to check electronics rack (dave)
- 2214 MX/Fire crew visit (tyler)
- 2219-2306 Isolate turbo pump at FCES (jordan, gerardo)