Reports until 15:26, Wednesday 27 April 2011
X1 SEI
corey.gray@LIGO.ORG - posted 15:26, Wednesday 27 April 2011 (762)
ISI Assembly Status

(Corey, Eric, Jim)

HAMISI#3 Status

Installed the large Walls & Flexure Walls on the Assembly, installed and ran all cabling, checked level and balanced the ISI.  Via the Dial Indicators, the level was good to within 0.001".  An Unlock/Lock check also saw the Dial Indicators stay within 0.001".

Shims used for Lockers:

For all intents and purposes, this ISI is ready to hand off to Vincent for testing.  What's left:  Get Test Stand up & running (Richard and crew?), Use new BSC/HAM Feedthru Interface, set gaps on Sensors, and then start testing this HAM.