TITLE: 03/14 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Commissioning
SHIFT SUMMARY: The morning was taken up by reverting IM and PR moves over the last few days, then ISCT1 work. Since then we have been trying to relock but an earthquake has been making this tricky. Starting to get past DRMI more consistently, currently powering up.
LOG:
Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
---|---|---|---|---|---|---|
15:06 | FAC | Karen | OptLab | n | Tech clean | 15:31 |
15:40 | - | Mitchell | LVEA | n | HAM6 pictures | 15:53 |
15:43 | Vac | Jordan | LVEA | n | HAM6 pictures as well | 15:53 |
15:55 | VAC | Chris | Outbuildings | n | SS unistrut hunt | 16:47 |
16:35 | FAC | Tyler | LVEA | n | Parts hunt | 16:36 |
16:58 | ISC | Sheila, TJ, Jennie | LVEA - ISCT1 | LOCAL | Alignment on ISCT1 | 19:22 |
17:28 | SQZ | Dhruva, Nutsinee | LVEA - SQZT7 | LOCAL | Homodyne work | 20:05 |
17:33 | FAC | Mitchell | EX, EY | n | FAMIS tasks | 18:13 |
18:34 | SQZ | Nutsinee, Dhruv, Naoki | SQZ table | y(local) | Squeezing even more | 22:51 |
19:04 | RUN | Gabriele | entire site | n | Running so far so fast | 20:53 |
20:10 | ISC | Sheila, Oli | LVEA | local | ISCT1 alignment | 20:53 |
20:58 | VAC | Travis | LVEA | n | Measurement | 21:01 |