TITLE: 03/27 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Observing
INCOMING OPERATOR: Oli
SHIFT SUMMARY: We've been locked for over 4.5 hours and have just transitioned back to Observing for the rest of the evening. The one lock loss we had was possibly cuased by work on the floor. Relocking was straight forward, I ended up moving PRM to lock PRMI in an attempt to avoid an initial alignment. It took 57 min to relock.
LOG:
Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
---|---|---|---|---|---|---|
16:09 | VAC | Gerardo | site | n | Forklifting septum from woodshop to LSB receiving | 16:39 |
16:09 | ISC | Sheila, Artem | CR | n | ESD bias change | 18:09 |
16:26 | ISC | Daniel | LVEA | n | Look at PSL racks | 16:45 |
16:46 | FAC | Kim | H2 | n | Tech clean | 18:46 |
17:11 | SQZ | Julian | OptLab | yes | SHG work | 19:32 |
20:09 | ISC | Sheila | LVEA | n | Checking on PSL racks | 20:29 |
22:12 | PEM | Robert | LVEA | n | Turn off amps, clean up | 22:17 |
22:19 | PEM | Robert | EX | n | Shaker meas | 23:14 |