910 – Tour of clean and bake for Professor Kajita from KAGRA, Pablo covering ops
930 – LVEA transitioned to Laser Hazard for IAS/SUS gap measurement
930 – Brief alarm on instrument air at EX…Kyle will investigate
1010 – Rick and Kiwamu giving quick tour in H1 PSL enclosure—area left in
commissioning mode
1020 – Corey cleaning up and setting up for TMS cable testing at Test Stand
1035 – Jeff working with suspensions near high bay roll up door
1200 – Richard transitioning LVEA to laser safe.
1320 – Alexa energizing Prometheus laser in old squeezer NHZ (LVEA East Bay enclosure)
***I took over for Justin around this time ***
1400 - Cheryl/Keita working on setting OSEMs on TMS at Test Stand