Displaying report 1-1 of 1.
Reports until 17:21, Friday 12 April 2024
H1 General (SQZ)
corey.gray@LIGO.ORG - posted 17:21, Friday 12 April 2024 (77143)
Back To Observing!

(Camilla,Corey,Naoki, Vicky)

Once H1 got through a few hiccups at the DRMI ASC & BSC St2 steps, it went straight to NLN. 

There were some Squeezer items which needed to be changed:

  1. PSAM Offset changes for ZM4 & ZM5 (under the TCSCS SDF) were ACCEPTED with Camilla's approval (see attached screenshot)
  2. ZM4/5/6 alignment changes needed---Naoki updated pointing & Camilla ACCEPTED the SDF.
  3. SQZ_MANAGER Guardian node needed to be transitioned to MANAGED---> Select MANAGED button on ALL screen
    • Plus SQZ_MANAGER needed to be listed as Managed by "ISC_LOCK"----> In a terminal entered:   caput H1:GRD-SQZ_MANAGER_MANAGER ISC_LOCK  (Vicky helped us with this)
Images attached to this report