Today's Activities: 9:15 - Apollo pier work began on HAM7 cleaning at Mid and End-X Kyle to soft-close GV5 H2 PSL enclosure construction HEPI post setup on HAM7 HEPI pier installation at BSC8 Dust Levels: Near the HAM7 work, dust monitor DST9_5 (5 micron monitor) had counts hovering around 10000 cts throughout most of the day with a spike of ~71000 cts lasting a few minutes during cleanup around the area at about ~15:30 PST.