Reports until 17:33, Wednesday 11 September 2013
LHO General
patrick.thomas@LIGO.ORG - posted 17:33, Wednesday 11 September 2013 (7730)
Ops Summary
Cheryl V., Jeff K., Kiwamu I., Patrick T. working on MC locking (alog 7729)
ARK staging roofing materials (WP 4126)
Apollo moving clean room in the LVEA (WP 4125)
Continuous communication problems with dust monitor 15 in the LVEA
One of Dale's students filing sharp edges off piece of old beam tube near the warehouse

09:00 Corey G. going to take pictures in the squeezer bay
09:17 Arnaud P. running transfer functions on TMSX
09:24 Andres & Jeff B. going to work on ITMX
09:47 Dave B. rebooted the DAQ to add GPS coordinates to the frame files
10:34 Andres & Jeff B. going to work on ITMX
12:37 Andres & Jeff B. going to work on ETMX
13:27 Thomas V. going to work on assembly baffle
14:50 Andres & Jeff B. back from end X
15:24 Arnaud P. going to LVEA to take hammer test measurements on cage of ITMX