Displaying report 1-1 of 1.
Reports until 16:20, Monday 10 June 2024
LHO General
corey.gray@LIGO.ORG - posted 16:20, Monday 10 June 2024 (78340)
Mon DAY Ops Summary

TITLE: 06/10 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Observing at 127Mpc
INCOMING OPERATOR: Tony
SHIFT SUMMARY:

For the morning H1 was in Observe (from Tony at 2am!) and shortly later we transitioned to Commissioning.  (much of this occurring under a glow of blue light from the visiting film crew!)  

The film crew completed multiple shots of Nergis, and filmed interviews with Sheila, Ibrahim, and Corey.  And we had lots of extras in the Control Room as well.  This work was mostly done after 1pm (they then moved to the Staging Building, LExC (early eve), and other shots?).
LOG:

Displaying report 1-1 of 1.