Shift started out with a windy morning and the Control Room in a post-power outage glitch state. Here are today's activities:
-
Recover from Power Outage. Back to normal around 11:15am (Jim & Dave)
-
Sheila restored PSL from the Outage
-
LVEA transitioned to Laser SAFE to install/swap HAM1 Feedthrus (went back to HAZARD in afternoon)
-
Cabling/fiber work at EX (Filiberto/Cyrus)
-
Arm Cavity Baffle work continues (Thomas)
-
SEI crew working on the BSC9 ISI (Jim & Hugh?)
-
Ken drilling on pedestals on Y-Beam Manifold for cable trays
-
Patrick did work with PSL & Dust monitors
-
HAM6 cabling/grounding work (Elec crew)