HughR, GregG, JimW
Today, we managed to get most of SEI's cables sorted and connected. Cable brackets were installed, unfortunately I forgot that the GS-13's need to be shorted to the ISI, until Hugh reminded me. Still need to fix corners 2 and 3. Otherwise, it went well, seismometer cables (unplugged at the pods) and CPS's are plugged into the chamber. I watched MEDM as Greg connected CPS's, and we ran an emulator on the seismometer cables, so we are pretty sure the right sensors are plugged into the right spots. Now, we are ready for TMS and SUS to go in, uncover, add the last of their hardware and plug in before SEI can float and balance.