anthony.sanchez@LIGO.ORG - posted 16:42, Monday 12 August 2024 (79525)
Monday Ops Day Shift End

TITLE: 08/12 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Corrective Maintenance
SHIFT SUMMARY:
H1 is in a vacuum pump down state since last week. We are still pumping down.
Current corner station vacuum pressure occording to VAC channel  H0:VAC-LY_Y1_PT120B_PRESS_TORR : 6.25e-07

VAC team decided to open the 2 of the 4 Gate valves today. This allows them to pump down with more vacuum pumps thus increaseing the rate at which the vacuum chamber is evacuated.

19:16 UTC Vacuum pressure high at BSC8, BSC2 and HAM6 This is because Gate Valve 1 was opened by Janos and Gerardo.
21:55 UTC Vacuum team opened Gate valve 2, this opened BSC7 to the rest of the CS.
GV7 was soft closed, I was monitoring H0:VAC-LX_X3_PT134B_PRESS_TORR and saw an increase in pressure.
23:23 UTC Janos put more pressure from the intrument air onto GV7 which stopped the increase in pressure at H0:VAC-LX_X3_PT134B_PRESS_TORR.

LOG:

Start Time System Name Location Lazer_Haz Task Time End
14:35 FAC Karen Optics & Vac Lab N Technical cleaning 14:53
15:40 FAC Karen & Kim LVEA N Technical Cleaning, Kim out, Karen still in. 18:08
19:05 VAC Gerado & Janos LVEA N Opening GV1 Between BCS8 and BSC1 19:42
21:30 VAC Gerardo & Janos LVEA N Opening Gate valve 2 22:30
21:52 FAC Tyler LVEA N Talking to Gerardo 22:22
22:42 VAC Gerardo Fil HAM Shaq No Running cables 23:36

 