oli.patane@LIGO.ORG - posted 08:08, Monday 19 August 2024 (79587)
Ops Day Shift Start

TITLE: 08/19 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Corrective Maintenance
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    SEI_ENV state: MAINTENANCE
    Wind: 4mph Gusts, 1mph 5min avg
    Primary useism: 0.01 μm/s
    Secondary useism: 0.07 μm/s
QUICK SUMMARY:

Vacuum pressure in BSC3 around 2.04e-07 (need to be around 8.8e-8), so probably no gate valves today. Over the weekend an earthquake from Japan tripped the ISI watchdogs for ITMY, BS, ETMX, and ETMY. Those have been untripped by TJ.