LHO General
cheryl.vorvick@LIGO.ORG - posted 17:13, Thursday 03 October 2013 (7979)
OPS

From Patrick:

CP2 being filled
9:40 Richard heading to end Y to help S & K electric with work on electrical circuit for fluorescent lights
9:40 Praxair delivery truck leaving
14:00 Kiwamu: PSL transition from commissioning to science (Paul want to make precise measurements) - delayed, so PSL is in commissioning mode.

EX:

Betsy and crew.

Chris doing electronics.

Disgnosis of odd dust monitor reading from yesterday, but not sure there's an alog yet.

 

OSB:

Roofers here working.

 

HAM1 work delayed - purge air is currently off - JohnW working on getting fixed

H1ASC went into alarm on overlow, which was real due to intentional misalignment of the IMC.