Reports until 15:07, Wednesday 11 September 2024
LHO General
tyler.guidry@LIGO.ORG - posted 15:07, Wednesday 11 September 2024 (80048)
VPW Heat Pump
The new Daikin heat pump that serves the clean side of the VPW has now been fully tied into the building and is running. One of the two cooling circuits appears to be DOA as it is completely flat. In the coming days Facilities team will pull a vacuum on the problematic lineset to assess whether it has a leak and if so, to what degree. In the meantime, the unit will still heat and, to a lesser degree, cool the spaces.

E. Otterman C. Soike T. Guidry