H2 INS
michael.rodruck@LIGO.ORG - posted 21:20, Monday 09 May 2011 (801)
H2 PSL installation

Air conditioner units were installed inside the PSL enclosure. They are hanging from threaded rods, suspended from the roof. The rods themselves are sitting on rubber machine mounts to isolate the units from the enclosure. Electrical conduit lines were installed as well.

Images attached to this report