TITLE: 09/23 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Observing at 152Mpc
INCOMING OPERATOR: Ryan S
SHIFT SUMMARY: Commissioning tasks completed: A2Ls gains, HAM1 PEM shaking tests, phasing POP9. We've been locked for a little over an hour, conditions are calm.
LOG:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 23:58 | SAF | H1 | LVEA | YES | LVEA is laser HAZARD | 18:24 |
| 14:30 | FAC | Karen | Optics lab, vac prep | N | Tech clean | 14:51 |
| 15:44 | PEM | Robert | LVEA | Y | Turn on HAM1 shaker | 15:48 |
| 16:00 | FAC | Karen | MidY | N | Tech clean | 17:04 |
| 16:30 | FAC | Kim | MidX | N | Tech clean | 17:17 |
| 16:45 | VAC | Janos | MidY | N | VAC checks, mech room | 17:26 |
| 16:47 | CAL | Tony | PCAL lab | Y | PCAL work, tues prep | 17:39 |
| 17:10 | PSL | Sheila | LVEA | N | Plug in cable at PSL racks | 17:15 |
| 18:32 | PEM | Robert | LVEA | Y | Turn off HAM1 shaker | 18:38 |
| 18:33 | PSL | Sheila | LVEA | Y | Unplug cable at PSL racks | 18:38 |
| 19:02 | CAL | Tony | PCAL lab | Y | PCAL work | 19:17 |
| 20:29 | CAL | Tony | PCAL lab | Y | PCAL work | 21:49 |
| 22:03 | CAL | Tony | PCAL lab | Y | PCAL work | 22:48 |