Reports until 16:30, Tuesday 15 October 2024
H1 General
anthony.sanchez@LIGO.ORG - posted 16:30, Tuesday 15 October 2024 (80694)
Tuesday Maintance Ops Shift End

TITLE: 10/15 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Observing at 156Mpc
INCOMING OPERATOR: Ibrahim
SHIFT SUMMARY:

Scheduled work to be done today for maintenance:
CDS - Frontend software work on h1sush7, h1cdsh8 and h1oaf0. (The firmware on these three frontends will be downgraded to production standard and these computers will be power cycled.)  Also adding strain relief - will isolate all corner computer systems to safe guard other work, 15 mins.

CDS - Implement the model changes needed for the strain gauge servos for ZM2, ZM4 and ZM5. This requires a model reboot of h1tcscs, as well as adding 3 channels to the copy guardian (Daniel)

09:00a -- SEI/SUS [CR] -- Measure HAM2ISI - PR3 cross-coupling. (Kissel) WP 12140

8am PSL - 1hr - Swap original NPRO controller back in since it didn't help glitches and has baggage (Ryan S)

9am - TCS - [CO2-Y Table] Take LVEA to laser hazard and prep for CO2Y swap. (Camilla) WP12121

9:30 - SQZ- beam profile of beam at pump ISS AOM, requires LVEA laser hazard (Sheila, Camilla) -- Postpwned

VAC - Filter Cavity Pump work end closest to FCES - FCT GVs closed near FCES

VAC - MY GV10 AIP work

SEI - HAM5 OLG script test (Ryan C, Jim) -- Postpwned

8h00 FAC - [ OSB R169] Disassembly/removal of old fume hood in the OSB Bake lab followed by any prep required for this space to be used differently. (T. Guidry, E. Otterman, C. Soike) WP12119  ????

FAC - DGR bringing EQ onsite, behind Staging Building ????


After  others, check CR - Biergarten SEI Guralp sensor huddle tests - temp BNC installed there and R3 ????

---------------------------------------------------------------------------

General Notes:
Many ISI Trips on HAM2 and ITMY during maintenance.
Norco N2 Refill at Y arm side of CS at 17:35UTC


Relocking Notes:
I.A: Moved PR2 after marking old Osem values to get Xarm to find IR.
Moving IMs after marking Osem values to get xarm to find IR. Once I got IM4 close ALIGN_IFO Took over.

20:29UTC Initial_Alignment finished and Locking started.

Hard Drive Failure in H1Guardian Server Raid Array, CDS Team Hot Swapped a Guardian hard drive see alog.

Lockloss from OMC_WHITENING [591]
 

LOG:

Start Time System Name Location Lazer_Haz Task Time End
15:04 FAC Karen, Kim, Nelly Ham Shaq N Technical cleaning 17:04
15:05 FAC Christina VPW N Forklifting 17:26
15:08 Vac Janos Mx N Pumping at MX and EX 19:32
15:11 PSL Ryan LVEA PSL Racks N Swapping PSL NPRO controller 16:03
15:14 VAC Gerardo LVEA N Getting cable from LVEA 16:03
15:19 TCS Camilla, McCarthy LVEA N Looking for parts 16:03
15:31 EE Fil PSL Rack & OutArm N Helping Ryan with PSL NPRO controller swap and Cable Trays near output arm 16:44
16:09 FAC Karen, Kim, Nelly EX, EY, HamShaq N Technical cleaning, Nelly out @ 16:47 17:44
16:17 CDS Dave & crew Remote N DAQ Restarts & SUS model upgrades. 17:07
16:18 VAC Travis, Jordan HAM Shaq N Turbo Pump work 18:11
16:25 TCS Camilla LVEA Yes LASER HAZARD Transition! WP12121 16:32
16:26 PR3 Kissel CtrlRm N Measure HAM2ISI - PR3 cross-coupling 19:03
16:36 SAFE HAZARD LVEA YES !!!!!LVEA IS LASER HAZARD!!!! 03:16
17:07 PSL Jason & Ryan Short LVEA YES adjusting injection currents 17:54
17:45 FAC Karen & Kim LVEA Yes Technical Cleaning, Karen Out 18:28 UTC 18:39
17:55 SAFE Fire Alarm Staging N Testing Fire Alarm functionality 19:55
18:08 PEM Lance & RyanS LVEA Yes Looking at PEM Coils 18:20
18:33 SEI RyanC ControlRoom N SEI HAM5 OLG script test 19:08
19:01 PSL Ryan S CtrlRm N Adjusting the PSL Rotation Stage 19:16
19:16 OPS Camilla LVEA Yes LVEA Sweep 19:56
19:57 EE Fil Mid Y N Picking up parts 20:17
21:48 PSL Jason, RyanS Optics Lab YES Working on new NPRO head 00:48
22:04 VAC Janos MidY N Checking Vac work at Mid station. 22:17
22:16 VAC Gerardo Mid Y N GB10 power supply swap 22:53