It's been a few days since either activity has been mentioned, therefore:
ITMx cartridge cleanroom has been cleared for access and the suspension is clamped, shielded, and bagged in prep for the flight likely to happen ~Monday. We still wait for elliptical baffle work to conclude before parking the ITMx cartridge in the baffle's alignment line-of-sight.
ETMx in-chamber alignment is still on hold after a stack up of longitudinal errors was found late last week. Two possible paths forward of where to take up the residual error (14mm) are under consideration.