DGR Storage Building Progress
Last week a bulk of the mobilization and earthwork began on the new storage building nearest the Staging Building. Footings are dug, and layout has begun. Beginning this week, the DGR team will shift from a 4-10 schedule to 5-8's as they start to build forms. They expect a forklift to be delivered sometime this morning and rebar to follow shortly after. The construction is presently ahead of schedule and the hope at this time is to begin pouring concrete as early as the end of next week.

T. Guidry 