filiberto.clara@LIGO.ORG - posted 15:27, Friday 18 October 2013 (8167)
H1 HEPI STS-2 Seismometers
Alog from yesterday. Did in-rack cabling for the STS-2 Seismometer Distribution Chassis for BSC1, BSC2 and BSC3. Each distribution chassis fans out to the HAM ISI chambers (HAM2-HAM6). The following schematics were used for reference: D0901301, D1000298, D1101576, and D1101584.

See attached for the physical location of each seismometer.

Filiberto Clara 