Reports until 16:35, Friday 18 October 2013
H1 SEI
greg.grabeel@LIGO.ORG - posted 16:35, Friday 18 October 2013 (8171)
End X HEPI
JimW GregG

HEPI actuator attachment started today at BSC9. Jim and I were able to get all of the vertical actuators attached with very little movement on the system so far. However, the vertical actuators are still locked and any moves to HEPI should be avoided until the install is finished.