tyler.guidry@LIGO.ORG - posted 14:54, Monday 13 January 2025 (82250)
DGR Storage Building Progress
Since the last report siding, insulation, roofing and doors have all been installed. In addition, a concrete transition between the asphalt and slab was poured as well as a walkway & equipment pad to/near the mandoor. With that, the building construction is complete. Keys were handed over last Thursday 1/9. I have began the process of populating the space with site equipment. Richard and I are making preparations to get basic electrical items ran to the building. 

T. Guidry