Reports until 10:42, Friday 25 October 2013
LHO General
john.worden@LIGO.ORG - posted 10:42, Friday 25 October 2013 (8262)
Roofing Progress

The LVEA roof has a complete membrane as of yesterday. The crew has started on the next level down and should be onto the office area roof in a week's time.

Next week sheet metal trim should finish up on some of the out buildings.

Photos are the LVEA roof.