jonathan.hanks@LIGO.ORG - posted 17:10, Thursday 06 February 2025 (82677)
WP 12317 Mounted a camera switch in the MSR for setup and testing
Tony Sanchez  mounted a cisco poe switch in the MSR for initial setup and testing.  Together we got the switch configured and hooked it up to the core switch.  This switch is named sw-lvea-aux1.  It will move into the CER racks and will act as a second camera switch.

Today we moved a test camera onto it and will be using this to continue our evaluation of h1digivideo4.