Reports until 10:05, Tuesday 11 February 2025
H1 ISC
sheila.dwyer@LIGO.ORG - posted 10:05, Tuesday 11 February 2025 (82740)
table of PR2 spot position vs measured power in ghost beam

Mayank, Sheila

We now have a number of power measurements at the HAM3 viewport, with corresponding estimates of the beam spot position on PR2 (from  July 2024 78878, yesterday's measurement of 8mW at PR3 yaw -74 urad 82722)

date range PR3 yaw slider value Y2L coefficient spot position on PR2 (in the plus Y direction from the center of the optic) power measured at HAM3 viewport [mW]
July 2018 until July 2024, except for a few days 152 -7.4 14.9 47  
July 5 2024 132     28
July 5 2024 110     19
July 5 2024 100     17
July 2024- Feb 6 2025 100 -6.25 12.588    
May 21st 2024, and Feb 6th- Feb 10th 2025 -74 -3 6 8  
Feb 10 2025 -230 to be measured   to be measured

We used Elenna's new calibration of PRC power 8724 to estimate that we have 2.53kW of power in the PRC beam.