Reports until 14:24, Monday 31 March 2025
H1 SQZ (DetChar)
camilla.compton@LIGO.ORG - posted 14:24, Monday 31 March 2025 (83665)
SQZ NLG increased from 11 to 19. ADF back on.

Today during commissioning we increased the SQZ NLG from 11 to 19, now the nominal OPO trans setpoint in sqzparams in 95uW. This was because before our last OPO crystal move 82134, the NLG was closer to 17-19.

We also turned the ADF (322Hz line) back on, it had been off since March 27th 83621, tagging DetChar.