H1 General
camilla.compton@LIGO.ORG - posted 13:59, Tuesday 01 April 2025 (83686)
ISCT1 and IOT2 moved away from HAM1/2, HAM2 Scaffolding Removed

TJ, Ibrahim, Betsy, Camilla, WPs 1242812414

We added guillotines to all VPs, removed the bellows and added yellow VP covers. IOT2 bellows were very tight so couldn't be removed until we moved the table an ~inch away from HAM2.  The tables bellows adapters were covered with ameristat and the bellows were covered with foil and placed on a nearby rack. Photo.

We moved the small garbing cleanroom up against the TSCY / the HAM3 cleanroom. We moved ISCT1 and IOT2 next to it on the other side of the racks, leaving space and a pallet for the HAM1 door. Photo. 

TJ and I removed and disassembled the HAM2 scaffolding and stored it with the other scaffolding in the High bay. 