Reports until 16:33, Tuesday 01 April 2025
LHO General
ibrahim.abouelfettouh@LIGO.ORG - posted 16:33, Tuesday 01 April 2025 (83688)
OPS Day Shift Summary

TITLE: 04/01 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:

IFO is in PLANNED ENGINEERING for VENT

Extremely productive first vent day in which the following planned tasks were completed:

As always, check out the trello for the most up to date vent news.

Guardian states are in the configurations attached in the screenshot

LOG:

Start Time System Name Location Lazer_Haz Task Time End
14:39 FAC Eric Woodshop N Activate Fire Pumps 16:21
15:05 EE Fil LVEA N HAM1/2 Table Enclosure Disconnect 23:52
15:10 FAC Kim, Nellie FCES N Technical Cleaning 15:39
15:12 OPS TJ LVEA N LVEA to Laser Extra Safe (Keys, Light Pipes etc) 15:30
15:34 PCAL Tony PCal Lab Local Meas. Setup 16:47
15:39 FAC Kim EX N Technical Cleaning 17:00
15:40 FAC Nellie EY N Technical Cleaning 16:22
16:09 AOS Betsy OptLab N Power meter 16:22
16:24 FAC Tyler, Eric LVEA N Scissor lift, Crane Work 18:27
16:24 SAF Camilla LVEA N Guillotine for viewports 19:05
16:26 VAC Janos, Gerardo, Travis, Jordan LVEA N Corner Vent Prep 19:25
16:26 EE Betsy LVEA N Checking on Fil team 17:11
16:36 AOS TJ LVEA N Wrap Bag Tag Help 19:05
16:46 SEI Jim LVEA N Locking HAM HEPIs 18:01
17:01 FAC Kim, Nellie LVEA N Technical cleaning 18:49
17:30 FAC Richard LVEA N HAM1 Conduit 17:45
17:43 AOS Ibrahim LVEA N Moving ISC tables 19:05
17:51 FAC Betsy LVEA N Looking at cabling 19:05
18:09 ISC Rahul, Mayank, Siva OptLab Local ISS array work 22:56
18:20 CAL Tony PcalLab Local Measurement setup 18:30
18:25 SEI Jim, Mitchell FCES, Ends N Picking up parts and FAMIS tasks 21:20
19:17 FAC Chris, Eric, Tyler, Randy LVEA N Cleanroom move 20:52
19:35 EE Oli LVEA N Helping Fil 22:29
19:43 VAC Gerardo LVEA N Cleanroom move help 22:06
19:58 AOS TJ, Camilla LVEA N Move Scaffolding by HAM1/2 20:34
20:07 VAC Janos, Jordan LVEA N Leak Checks 22:06
20:14 PCAL Tony PCAL Lab N PCAL Meas. 20:20
20:46 ALS TJ EX, EY N Turning on ALS 21:27
20:56 FAC Tyler LVEA N Sock Swap 21:38
21:33 TCS Matt, Camilla OptLab Local CO2 Table Work 22:56
21:52 SEI Mitchell LVEA N Seismic Assy Size Verification 21:58
21:53 AOS Betsy LVEA N Walkabout 22:33
22:06 EE Marc LVEA N Helping Fil and Oli with HAM 1/2 Table Enclosures 00:05
22:07 VAC Janos LVEA N Leak Checks 22:41
22:41 VAC Travis, Gerardo, Jordan LVEA N   23:41
22:42 FAC Tyler LVEA N Rigging Transportation 22:53
23:14 AOS Betsy LVEA N   23:25
23:29 OPS Ryan C LVEA N Dust monitor connectiom 00:29
Images attached to this report