WP 12424
The field cabling for RM1 and RM2 was disconnected in the CER and field rack. Cables were pulled back from ISC-R4 to SUS-R1. Cables were installed early on and buried in the cable tray. It was decided to cut the connector to ease cable work. Ends will need to be re-terminated. The PM1 field cables arrived onsite and will be installed tomorrow. Work will be outside the HAM1/2 clean room.
WP 12393
The SEI field cables were pulled to the following HAM1 flange locations:
Corner 1 (GS-13, L4C, ISI Coil Drive) to Flange D1
Corner 2 (GS-13, L4C, ISI Coil Drive) to Flange D5
Corner 3 (GS-13, L4C, ISI Coil Drive) to Flange D3
HEPI Corner 1&2 to Flange D5
HEPI Corner 3 to Flange D3
WP 12421
Cabling to IOHT2L and ISCT1 was disconnected. Both sets of cables were pulled out of the clean room, clear of any HAM1 activities. The safety interlock system was tripped when cables were being moved off ISCT1. Safety system was restored. The field EtherCAT field boxes EL1908 and cables are located on top of HAM1. They should not interfere with door removal/install.
WP 12422
The vertical cable tray, conduit and part of the floor cable tray was removed to clear the HAM ISI Installation Fixture. Cables to ISCT1 are now routed along the cable tray outside of the clean room.
We took time to pull out various DB cables, fibers, RF cables ect that were not being used. Area around HAM1 is now clear. Let us know you see or need anything else moved/cleared for the ISI install.
F. Clara, O. Patane, M. Pirello