TITLE: 04/02 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: MAINTENANCE
Wind: 6mph Gusts, 4mph 3min avg
Primary useism: 0.17 μm/s
Secondary useism: 0.17 μm/s
QUICK SUMMARY:
IFO is in PLANNED ENGINEERING for the vent.
Today's vent tasks:
- Crane engine hoist to BSC8 (FAC)
- Inspect HAM1 and BSC8 final cleanroom (FAC)
- Turn on HAM1 cleanroom and garb room (FAC)
- Power down ISC chassis that will be recabled (Fil/EE)
- Pull ISC cables - NOT COAX yet and work to relabel (Fil/EE)
- HAM1 Offload HEPI Setup (SEI/Jim/Mitchell)
- Leak check corner under vac (VAC)
- Prep for corner vent (VAC)
- Checklist for HAM1 vent (VAC)
- HAM1 1st cleaning (Kim/Nellie/FAC)
- Clean out recieving for ISI (FAC)
- HAM6 Guage Work (VAC)
- Checklist for corner vent (VAC)
- Move forklift to HAM1 south bay area (FAC)
- Crane or move power bang box to southbay for cleanrooms (FAC)
- Replace ~3ft of cleanroom panel for HAM2 +Y-X (FAC)
- Vent HAM1 (VAC)
- Start HAM1 bolt removal (VAC/Randy)
- Move HAM1 cleanroom into final place (5 people)
- Stock garb room by HAM3 (FAC/Kim)
- Prep laydown areas for stack deinstall, setup door pallet at HAM3+Y
- Get dust mons working and trending (OPS/RyanC)
Work safe!